New burner installation for Duyvis

Duyvis has a long history. In 1806, Teewis Duyvis produced animal feed with his oil mill. Later, sauces and oils were added. In 1961, the Duyvis family started selling peanuts and nuts. Savory snacks and dips followed seven years later. This marked the beginning of Duyvis as we know it today.

Compliance with emission requirements

In 2016, Duyvis decided to replace the existing burner installation. This was necessary due to the emission requirement effective from January 1, 2017: 70 mg/m³ at 3% O₂. Under the new Activities Decree, existing installations must also comply with this requirement.

Project details

Completion: 2016
Company details: Duyvis, Zaandam
Crop: Cocktail nuts
Burner type: TR 1.0 ND LMV Gas
Boiler capacity: 998 Mcal / 1,160 kW
Gas consumption full load: 143 nm3/h

View our
other projects

Unigas Novumax combination in collaboration with HoSt Bioenergy

Borst Tulips

New heating installation with low NOx burner remains well below the 50 mg requirement for Green Label Greenhouse at 34.1 mg/m³.

Electric boilers for Van Gog Kwekerijen

Electric boilers fill buffers during low electricity prices. This ensures energy is used smartly and costs remain manageable in practice.

RKB burner PanAmerican Seed Hem

Ateco worked on a new boiler house with a heating installation and Zantingh RKB compact burner for PanAmerican Seed in Hem.

Cryonorm Vaporizer

The test setup for a new gas vaporizer went into operation at Cryonorm, featuring a specially designed RKB 5.0 from Zantingh.

Pre-assembled burner installation U.S.A.

Zantingh designed three burner installations that were completely assembled, tested, and prepared for transport in the workshop.